Rohbau
|
|
Monat
|
April
|
Mai
|
Juni
|
Juli
|
| Kalenderwoche |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
| Fundament |
 |
 |
|
|
|
|
|
|
|
|
|
|
|
|
| Bodenplatte |
 |
 |
|
|
|
|
|
|
|
|
|
|
|
|
| Erdgeschossdecke |
|
 |
 |
 |
|
|
|
|
|
|
|
|
|
|
| Bautreppe |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Gerüst |
|
|
|
 |
|
|
|
|
|
|
|
|
 |
|
| Giebel |
|
|
|
|
 |
 |
|
|
|
|
|
|
|
|
| Dachstuhl |
|
|
|
|
 |
 |
|
|
|
|
|
|
|
|
| Dacheindeckung |
|
|
|
|
|
 |
 |
|
|
|
|
|
|
|
| Fenster |
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
| Außenputz |
|
|
|
|
|
|
|
 |
|
|
|
 |
 |
|
|
Ausbau
|
|
Monat
|
Juni
|
Juli
|
August
|
| Kalenderwoche |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
32 |
33 |
34 |
35 |
| Trockenbau roh |
 |
 |
 |
|
|
|
|
|
|
|
|
|
|
|
| Trockenbau fertig |
|
|
|
|
|
|
 |
 |
 |
|
|
|
|
|
| HLS / Elektro |
 |
 |
 |
|
|
|
|
|
|
|
|
|
|
|
| Blower Door Test |
|
|
 |
 |
|
|
|
|
|
|
|
|
|
|
| Innenputz |
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
| Estrich |
|
|
|
|
 |
Trockenzeit |
|
|
|
|
| Heizung fertig |
|
|
|
|
|
|
 |
 |
 |
|
|
|
|
|
| Elektro fertig |
|
|
|
|
|
|
 |
 |
|
|
|
|
|
 |
| Fließen |
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
| Sanitär fertig |
|
|
|
|
|
|
|
|
|
|
|
 |
 |
|
| Innentüren |
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
| Treppe |
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|